| OVERALL PROJECT BID SCHEDULE | |||
|---|---|---|---|
| Package | Scopes | Planned Bid Period | Comments |
| Enabling | Trailers, Fence, Site Development, and Site Logistic Support Items | Complete | Complete |
| Design-Assist | Structural Steel, Baggage Handling System, Mechanical and Plumbing, Electrical, Low Voltage, and Ground Improvements | Complete | Complete |
| Foundations | Deep Foundations, Shallow Foundations, and Long Lead Equipment | Complete | Complete |
| ITB | Apron Paving, Fueling System, Guideway, and Passenger Boarding Bridges http://www.airsided.com/ | Current | Issued by HCAA |
| Airside D | Core & Shell, Interiors, and MEP Systems | Quarter 4, 2025 | Detailed Bid Schedule Forthcoming |