Bidding Opportunities

OVERALL PROJECT BID SCHEDULE
PackageScopesPlanned Bid PeriodComments
EnablingTrailers, Fence, Site Development, Site Logistic Support ItemsQuarter 3, 2024Detailed Enabling Schedule Below
BaggageBaggage Design BuildQuarter 1, 2025Detailed Bid Schedule Forthcoming
ITBApron Paving, Fueling System, Guideway, Passenger Boarding BridgesQuarter 2, 2025Detailed Bid Schedule Forthcoming
FoundationsDeep Foundations, Shallow Foundations, Long Lead EquipmentQuarter 3, 2025Detailed Bid Schedule Forthcoming
Airside DCore & Shell, Interiors, MEP SystemsQuarter 4, 2025Detailed Bid Schedule Forthcoming

Enabling Bid SchedulePlanned Dates
Publish Invitation to Bidders with Plans & SpecsAugust 21, 2024
Pre Bid Meeting & Site WalkAugust 28, 2024
RFI's DeadlineAugust 30, 2024
Bids DueSeptember 18, 2024